Home Projects

On-going Projects

Improvement of Drains at Pualu Punggol Barat​ Gallery Image 5
Improvement of Drains at Pualu Punggol Barat​ Gallery Image 1
Improvement of Drains at Pualu Punggol Barat​ Gallery Image 2
Improvement of Drains at Pualu Punggol Barat​ Gallery Image 3
Improvement of Drains at Pualu Punggol Barat​ Gallery Image 4
Improvement of Drains at Pualu Punggol Barat_ Gallery Image 6
Improvement of Drains at Pualu Punggol Barat​ Gallery Image 5
Improvement of Drains at Pualu Punggol Barat​ Gallery Image 1
Improvement of Drains at Pualu Punggol Barat​ Gallery Image 4
Improvement of Drains at Pualu Punggol Barat_ Gallery Image 6
Improvement of Drains at Pualu Punggol Barat​ Gallery Image 5
Improvement of Drains at Pualu Punggol Barat​ Gallery Image 1
Improvement of Drains at Pualu Punggol Barat​ Gallery Image 2
Improvement of Drains at Pualu Punggol Barat​ Gallery Image 3
Improvement of Drains at Pualu Punggol Barat​ Gallery Image 4
Improvement of Drains at Pualu Punggol Barat_ Gallery Image 6
Improvement of Drains at Pualu Punggol Barat​ Gallery Image 5
Improvement of Drains at Pualu Punggol Barat​ Gallery Image 1
Improvement of Drains at Pualu Punggol Barat​ Gallery Image 2
Improvement of Drains at Pualu Punggol Barat​ Gallery Image 3
Description Improvement of Drains at Pualu Punggol Barat​
Client PUB​
Contract Value ​S$ 40,956,566.00​
Contract Period Jan 2022 – Jul 2025​​
Scope of Works Roadside Drain, Box Culvert including traffic diversion &
Outfall Construction​​
on going projects of road construction image 5
on going projects of road construction image 6
on going projects of road construction image 2
on going projects of road construction image 1
on going projects of road construction image 3
on going projects of road construction image 5
on going projects of road construction image 6
on going projects of road construction image 1
on going projects of road construction image 3
on going projects of road construction image 5
on going projects of road construction image 6
on going projects of road construction image 2
on going projects of road construction image 1
on going projects of road construction image 3
on going projects of road construction image 5
on going projects of road construction image 6
on going projects of road construction image 2
on going projects of road construction image 1
Description Construction of Roads, Drains, Sewers & Ancillary Works at Seletar Aerospace Avenue & Road 3​
Client JTC​​
Contract Value ​S$ 7,533,623.00​​
Contract Period Sep 2020 – Dec 2025​​​
Scope of Works Sewers, Drains including box culvert with traffic diversion & Roadworks with bus stop construction​
Improvement to Yishun Avenue Gallery Image 5
Improvement to Yishun Avenue Gallery Image 1
Improvement to Yishun Avenue Gallery Image 2
Improvement to Yishun Avenue Gallery Image 3
Improvement to Yishun Avenue Gallery Image 4
Improvement to Yishun Avenue Gallery Image 5
Improvement to Yishun Avenue Gallery Image 1
Improvement to Yishun Avenue Gallery Image 3
Improvement to Yishun Avenue Gallery Image 4
Improvement to Yishun Avenue Gallery Image 5
Improvement to Yishun Avenue Gallery Image 1
Improvement to Yishun Avenue Gallery Image 2
Improvement to Yishun Avenue Gallery Image 3
Improvement to Yishun Avenue Gallery Image 4
Improvement to Yishun Avenue Gallery Image 5
Improvement to Yishun Avenue Gallery Image 1
Improvement to Yishun Avenue Gallery Image 2
Improvement to Yishun Avenue Gallery Image 3
Description Improvement to Yishun Avenue 3 Outlet Drain (Yishun Ring Road, Yishun Avenue 3 and Yishun Central)​
Client PUB​
Contract Value ​S$ 58,324,966.00​
Contract Period Jan 2024 – Jan 2028​​​
Scope of Works Roadside Drains, Box culvert including traffic diversion, PCN with footbridge & Covered Linkway with bus stop construction
Proposed Infrastructure Works Gallery Image 4
Proposed Infrastructure Gallery Image 1
Proposed Infrastructure Works Gallery Image 1
Proposed Infrastructure Works Gallery Image 5
Proposed Infrastructure Works Gallery Image 2
Proposed Infrastructure Works Gallery Image 3
Proposed Infrastructure Works Gallery Image 4
Proposed Infrastructure Gallery Image 1
Proposed Infrastructure Works Gallery Image 2
Proposed Infrastructure Works Gallery Image 3
Proposed Infrastructure Works Gallery Image 4
Proposed Infrastructure Gallery Image 1
Proposed Infrastructure Works Gallery Image 1
Proposed Infrastructure Works Gallery Image 5
Proposed Infrastructure Works Gallery Image 2
Proposed Infrastructure Works Gallery Image 3
Proposed Infrastructure Works Gallery Image 4
Proposed Infrastructure Gallery Image 1
Proposed Infrastructure Works Gallery Image 1
Proposed Infrastructure Works Gallery Image 5
Description Proposed Infrastructure Works At Ayer Merbau Road, Jurong Island
Client JTC​​
Contract Value ​S$ 15,929,438.00​​​
Contract Period May 2024 – Dec 2027​​​​
Scope of Works Ground Improvement, Sewers, Drains including box culvert & Roadworks with traffic diversion​

Completed Projects in Last 10 Years

Proposed Site Gallery Image 5
Proposed Site Gallery Image 1
Proposed Site Gallery Image 1 1
Proposed Site Gallery Image 2 1
Proposed Site Gallery Image 3 1
Proposed Site Gallery Image 4 1
Proposed Site Gallery Image 5 1
Proposed Site Gallery Image 3
Proposed Site Gallery Image 4
Proposed Site Gallery Image 5
Proposed Site Gallery Image 1
Proposed Site Gallery Image 3
Proposed Site Gallery Image 4
Proposed Site Gallery Image 5
Proposed Site Gallery Image 1
Proposed Site Gallery Image 1 1
Proposed Site Gallery Image 2 1
Proposed Site Gallery Image 3 1
Proposed Site Gallery Image 4 1
Proposed Site Gallery Image 5 1
Proposed Site Gallery Image 3
Proposed Site Gallery Image 4
Proposed Site Gallery Image 5
Proposed Site Gallery Image 1
Proposed Site Gallery Image 1 1
Proposed Site Gallery Image 2 1
Description Proposed Site Clearance at Woodlands Wafer Fab Park​
Client JTC​​
Contract Value ​S$ 5,524,020.00​
Contract Period Dec 2023​
Scope of Works EMMP, Tree Felling works, Site Clearance, Earthworks including Slope Stabilization & Cut-off Drain construction​
proposed drainage scheme completed set b gallery image 4
proposed drainage scheme completed set b gallery image 6
Proposed Drainage Gallery Image 2
proposed drainage scheme completed set b gallery image 3
proposed drainage scheme completed set b gallery image 2
proposed drainage scheme completed set b gallery image 5
proposed drainage scheme completed set b gallery image 1
proposed drainage scheme completed set b gallery image 4
proposed drainage scheme completed set b gallery image 6
proposed drainage scheme completed set b gallery image 5
proposed drainage scheme completed set b gallery image 1
proposed drainage scheme completed set b gallery image 4
proposed drainage scheme completed set b gallery image 6
Proposed Drainage Gallery Image 2
proposed drainage scheme completed set b gallery image 3
proposed drainage scheme completed set b gallery image 2
proposed drainage scheme completed set b gallery image 5
proposed drainage scheme completed set b gallery image 1
proposed drainage scheme completed set b gallery image 4
proposed drainage scheme completed set b gallery image 6
Proposed Drainage Gallery Image 2
proposed drainage scheme completed set b gallery image 3
Description Proposed Drainage Scheme In Changi East​
Client PUB
Contract Value ​S$ 9,500,000.00​​​​
Contract Period Oct 2022​​​​​
Scope of Works Drain Construction including connection to the Outlet Drain, Box Culvert construction including traffic diversion
Construction of Roads Drains And Sewers at Pulau Pesek Jurong Island Gallery Image 4
Construction of Roads Drains And Sewers at Pulau Pesek Jurong Island Gallery Image 1
Construction of Roads Drains And Sewers at Pulau Pesek Jurong Island Gallery Image 5
Construction of Roads Completed Last 10 Years Gallery Image 3
Construction of Roads Drains And Sewers at Pulau Pesek Jurong Island Gallery Image 2
Construction of Roads Drains And Sewers at Pulau Pesek Jurong Island Gallery Image 3
Construction of Roads Drains And Sewers at Pulau Pesek Jurong Island Gallery Image 4
Construction of Roads Drains And Sewers at Pulau Pesek Jurong Island Gallery Image 1
Construction of Roads Drains And Sewers at Pulau Pesek Jurong Island Gallery Image 2
Construction of Roads Drains And Sewers at Pulau Pesek Jurong Island Gallery Image 3
Construction of Roads Drains And Sewers at Pulau Pesek Jurong Island Gallery Image 4
Construction of Roads Drains And Sewers at Pulau Pesek Jurong Island Gallery Image 1
Construction of Roads Drains And Sewers at Pulau Pesek Jurong Island Gallery Image 5
Construction of Roads Completed Last 10 Years Gallery Image 3
Construction of Roads Drains And Sewers at Pulau Pesek Jurong Island Gallery Image 2
Construction of Roads Drains And Sewers at Pulau Pesek Jurong Island Gallery Image 3
Construction of Roads Drains And Sewers at Pulau Pesek Jurong Island Gallery Image 4
Construction of Roads Drains And Sewers at Pulau Pesek Jurong Island Gallery Image 1
Construction of Roads Drains And Sewers at Pulau Pesek Jurong Island Gallery Image 5
Construction of Roads Completed Last 10 Years Gallery Image 3
Description Construction of Roads, Drains And Sewers at Pulau Pesek, Jurong Island Highway​
Client JTC
Contract Value ​S$ 9,283,633.00​
Contract Period Feb 2022​
Scope of Works Vibro Compaction Works, Sewer & MH Construction, Drain Construction including outfall with security cage & Roadworks
Proposed Construction of Infrastructure Works completed gallery image 1
Proposed Construction Gallery Image 1
Proposed Construction Gallery Image 2
Proposed Construction of Infrastructure Works completed gallery image 3
Proposed Construction of Infrastructure Works completed gallery image 2
Proposed Construction of Infrastructure Works completed gallery image 4
Proposed Construction of Infrastructure Works completed gallery image 5
Proposed Construction of Infrastructure Works completed gallery image 1
Proposed Construction Gallery Image 1
Proposed Construction of Infrastructure Works completed gallery image 4
Proposed Construction of Infrastructure Works completed gallery image 5
Proposed Construction of Infrastructure Works completed gallery image 1
Proposed Construction Gallery Image 1
Proposed Construction Gallery Image 2
Proposed Construction of Infrastructure Works completed gallery image 3
Proposed Construction of Infrastructure Works completed gallery image 2
Proposed Construction of Infrastructure Works completed gallery image 4
Proposed Construction of Infrastructure Works completed gallery image 5
Proposed Construction of Infrastructure Works completed gallery image 1
Proposed Construction Gallery Image 1
Proposed Construction Gallery Image 2
Proposed Construction of Infrastructure Works completed gallery image 3
Description Proposed Construction of Infrastructure Works (Roads, Drains, Sewers & Ancillary Works) at Lorong Halus (Phase 2)
Client JTC
Contract Value ​S$ 18,000,000.00​
Contract Period Sep 2021​
Scope of Works Stone Column, Sewer, Landfill Capping Layer Reinstatement, Drain works including Trapezoidal drain to the outlet drain & Roadworks
Nominated Sub contract for Construction gallery image 1
Nominated Sub contract for Construction gallery image 2
Nominated Sub contract for Construction gallery image 4
Nominated Sub contract for Construction gallery image 3
Nominated Sub contract for Construction gallery image 1
Nominated Sub contract for Construction gallery image 2
Nominated Sub contract for Construction gallery image 4
Nominated Sub contract for Construction gallery image 3
Nominated Sub contract for Construction gallery image 1
Nominated Sub contract for Construction gallery image 2
Nominated Sub contract for Construction gallery image 4
Nominated Sub contract for Construction gallery image 3
Nominated Sub contract for Construction gallery image 1
Nominated Sub contract for Construction gallery image 2
Nominated Sub contract for Construction gallery image 4
Nominated Sub contract for Construction gallery image 3
Description Nominated Sub-contract for Construction of Service Tunnels for Reclamation at Jurong Island Westward Extension
Client JTC
Contract Value ​S$ 34,800,000.00​
Contract Period Mar 2021​​
Scope of Works Construction of deep excavation service tunnels along with the infrastructure development works
Ground Improvement Works at Changi East gallery image 2
Ground Improvement Works at Changi East gallery image 5
Ground Improvement Works Gallery Image 2
Ground Improvement Works at Changi East gallery image 1
Ground Improvement Works at Changi East gallery image 4
Ground Improvement Works at Changi East gallery image 3
Ground Improvement Works at Changi East gallery image 2
Ground Improvement Works at Changi East gallery image 5
Ground Improvement Works at Changi East gallery image 4
Ground Improvement Works at Changi East gallery image 3
Ground Improvement Works at Changi East gallery image 2
Ground Improvement Works at Changi East gallery image 5
Ground Improvement Works Gallery Image 2
Ground Improvement Works at Changi East gallery image 1
Ground Improvement Works at Changi East gallery image 4
Ground Improvement Works at Changi East gallery image 3
Ground Improvement Works at Changi East gallery image 2
Ground Improvement Works at Changi East gallery image 5
Ground Improvement Works Gallery Image 2
Ground Improvement Works at Changi East gallery image 1
Description Ground Improvement Works at Changi East Industrial Zone for Changi East Development
Client CAG
Contract Value ​S$ 12,556,667.00​
Contract Period Mar 2021​
Scope of Works Pre drilling / augering to loosen the soil, installation of PVD, Surcharging works & Retaining sand bag wall for surcharge slope
construction of infrastructure completed gallery image 5
Construction of Infrastructure Gallery Image 1
Construction of Infrastructure Gallery Image 2
Construction of Infrastructure Gallery Image 3
Construction of Infrastructure Gallery Image 4
Construction of Infrastructure Gallery Image 5
construction of infrastructure completed gallery image 5
Construction of Infrastructure Gallery Image 1
Construction of Infrastructure Gallery Image 4
Construction of Infrastructure Gallery Image 5
construction of infrastructure completed gallery image 5
Construction of Infrastructure Gallery Image 1
Construction of Infrastructure Gallery Image 2
Construction of Infrastructure Gallery Image 3
Construction of Infrastructure Gallery Image 4
Construction of Infrastructure Gallery Image 5
construction of infrastructure completed gallery image 5
Construction of Infrastructure Gallery Image 1
Construction of Infrastructure Gallery Image 2
Construction of Infrastructure Gallery Image 3
Description Construction of Infrastructure Works at Finger 1 Phase 2a
Client JTC
Contract Value ​S$ 8,885,785.00​​
Contract Period Mar 2020​
Scope of Works Vibro Compaction works, Sewer pipe laying works, Drain works including trapezoidal drain and Roadworks
Construction of Roads completed gallery image 6
Construction of Roads completed gallery image 1
Construction of Roads completed gallery image 5
Construction of Roads completed gallery image 4
Construction of Roads Phase 2 Waterfront Land Gallery Image 4
Construction of Roads completed gallery image 3
Construction of Roads completed gallery image 2
Construction of Roads completed gallery image 6
Construction of Roads completed gallery image 1
Construction of Roads completed gallery image 3
Construction of Roads completed gallery image 2
Construction of Roads completed gallery image 6
Construction of Roads completed gallery image 1
Construction of Roads completed gallery image 5
Construction of Roads completed gallery image 4
Construction of Roads Phase 2 Waterfront Land Gallery Image 4
Construction of Roads completed gallery image 3
Construction of Roads completed gallery image 2
Construction of Roads completed gallery image 6
Construction of Roads completed gallery image 1
Construction of Roads completed gallery image 5
Construction of Roads completed gallery image 4
Description Construction of Roads, Drains & Sewer at Tuas South Link 4 and Finger One Phase 2 Waterfront Land
Client JTC​
Contract Value ​S$ 19,739,666.00​
Contract Period Jul 2018​​
Scope of Works 35m & 45m Wide U-Drain with the rock revetment works
Drainage Works Completed Gallery Image 5
Drainage Works For Collector Drain II At Changi completed gallery image 1
Drainage Works For Collector Drain II At Changi completed gallery image 2
Drainage Works For Collector Drain II At Changi completed gallery image 3
Drainage Works For Collector Drain II At Changi completed gallery image 4
Drainage Works For Collector Drain II At Changi completed gallery image 5
Drainage Works Completed Gallery Image 1
Drainage Works Completed Gallery Image 2
Drainage Works Completed Gallery Image 4
Drainage Works Completed Gallery Image 5
Drainage Works For Collector Drain II At Changi completed gallery image 1
Drainage Works Completed Gallery Image 2
Drainage Works Completed Gallery Image 4
Drainage Works Completed Gallery Image 5
Drainage Works For Collector Drain II At Changi completed gallery image 1
Drainage Works For Collector Drain II At Changi completed gallery image 2
Drainage Works For Collector Drain II At Changi completed gallery image 3
Drainage Works For Collector Drain II At Changi completed gallery image 4
Drainage Works For Collector Drain II At Changi completed gallery image 5
Drainage Works Completed Gallery Image 1
Drainage Works Completed Gallery Image 2
Drainage Works Completed Gallery Image 4
Drainage Works Completed Gallery Image 5
Drainage Works For Collector Drain II At Changi completed gallery image 1
Drainage Works For Collector Drain II At Changi completed gallery image 2
Drainage Works For Collector Drain II At Changi completed gallery image 3
Description Drainage Works For Collector Drain II At Changi East Reclamation Area A
Client PUB
Contract Value ​S$ 38,122,586.00​
Contract Period Jun 2016​
Scope of Works 35m & 45m Wide U-Drain with the rock revetment works​
Proposed Construction of Roads Drains Set A gallery image 3
Proposed Construction of Roads Drains Set A gallery image 4
coffee dam
Proposed Construction of Roads Gallery Set 1 Image 3
Proposed Construction of Roads Gallery Set 1 Image 4
Proposed Construction of Roads Gallery Set 1 Image 5
Proposed Construction of Roads Drains Set A gallery image 1
Proposed Construction of Roads Drains Set A gallery image 2
Proposed Construction of Roads Drains Set A gallery image 3
Proposed Construction of Roads Drains Set A gallery image 4
Proposed Construction of Roads Drains Set A gallery image 1
Proposed Construction of Roads Drains Set A gallery image 2
Proposed Construction of Roads Drains Set A gallery image 3
Proposed Construction of Roads Drains Set A gallery image 4
coffee dam
Proposed Construction of Roads Gallery Set 1 Image 3
Proposed Construction of Roads Gallery Set 1 Image 4
Proposed Construction of Roads Gallery Set 1 Image 5
Proposed Construction of Roads Drains Set A gallery image 1
Proposed Construction of Roads Drains Set A gallery image 2
Proposed Construction of Roads Drains Set A gallery image 3
Proposed Construction of Roads Drains Set A gallery image 4
coffee dam
Proposed Construction of Roads Gallery Set 1 Image 3
Description Proposed Construction of Roads, Drains, and Outfall Structure at Tuas South Boulevard, Tuas South Ave. 5, 7 and 16
Client Koon / JTC​
Contract Value ​S$ 40,800,000.00​
Contract Period May 2015​
Scope of Works Roadside drains including outfall construction to the sea with PCG security cage & Roadworks
Proposed Construction of Roads Completed Set B Gallery Image 5
Proposed Construction of Roads Completed Set B Gallery Image 1
Proposed Construction of Roads Completed Set B Gallery Image 2
Proposed Construction of Roads Completed Set B Gallery Image 3
Proposed Construction of Roads Completed Set B Gallery Image 4
Proposed Construction of Roads Completed Set B Gallery Image 5
Proposed Construction of Roads Completed Set B Gallery Image 1
Proposed Construction of Roads Completed Set B Gallery Image 3
Proposed Construction of Roads Completed Set B Gallery Image 4
Proposed Construction of Roads Completed Set B Gallery Image 5
Proposed Construction of Roads Completed Set B Gallery Image 1
Proposed Construction of Roads Completed Set B Gallery Image 2
Proposed Construction of Roads Completed Set B Gallery Image 3
Proposed Construction of Roads Completed Set B Gallery Image 4
Proposed Construction of Roads Completed Set B Gallery Image 5
Proposed Construction of Roads Completed Set B Gallery Image 1
Proposed Construction of Roads Completed Set B Gallery Image 2
Proposed Construction of Roads Completed Set B Gallery Image 3
Description Proposed Construction of Roads, Drains, Sewers, Services Tunnels & Soil Improvement Works at Meranti Avenue, Jurong Island Phase 1​
Client JTC
Contract Value ​S$ 19,665,666.00
Contract Period Oct 2011
Scope of Works Vibro compaction works, Service tunnels, Sewer & MH construction, Drain works including box culvert & Roadworks

Completed Projects in Last 10 Years

as Main Contractor

No. Project Title Owner Contract Amt
1 Turfing And Ground Reinstatement Works At Tuas View JTC $ 246,433.05
2 Proposed Earthworks, Demolition of Existing Roads & Drains, Additional Services Diversion and Construction of Cul-De-Sac & Drains At Tampines Industrial Estate JTC $ 1,067,776.00
3 ​Proposed Bulk Liquid Products Terminal at Jurong Island – Concrete Pavement Works (‘Base Offer’) Horizon $ 3,599,566.00
4 Proposed Road Widening Works At Alps Ave JTC $ 392,956.00
5 Demetalling works on Pulau Pawai DSTA $ 109,996.00
6 Proposed Construction of Roads And Drains At Woodlands Ave 12 (Phase 1) JTC $ 739,000.00
7 Proposed Erection of 2nos. 2-storey Security Tower at Jurong Island JTC $ 1,930,107.00
8 Proposed Dredging Works at Jurong Lake PUB $ 6,566,656.00
9 Proposed Construction of Temporary Road for Diversion of West Camp Road & Seletar Club Road JTC $ 6,566,656.00
10 Improvement to Roadside Drains III Western Sector Contract 2 – Jurong Port & Jalan Buroh Areas PUB $ 9,599,656.00
11 Soil Improvement Works at Pasir Ris DSTA $ 5,631,333.00
12 Proposed Boardwalks, Water Features and Wetlands at Jurong Lake PUB $ 6,656,566.00
13 Proposed Desilting of Kallang River (From Braddell Road to Nicoll Highway) and Part of Rochor Canal (Downstream of Crawford Bridge) PUB $ 1,629,524.28
14 Proposed Land Preparation Works at North Coast Drive JTC $ 1,670,105.00
15 Improvement to Drains at Benoi Sector Area PUB $ 5,999,555.00
16 Proposed Plumbing & Piping Services, Sanitary & Fire Protection Installation for Proposed Docks, Wharves, Quay and Other Ancillary Works in New Shipyard (Phase 1) Jurong Shipyard $ 2,105,000.00
17 Proposed Construction of Roads, Drains and Sewers at Wenya (Phase 1) JTC $ 13,499,555.00
18 Proposed Erecton of Workshops, Warehouse, Temporary Ancillary Workers’ Dormitory (For 9408 Workers) and Ancillary Buildings for Shipyard Development on Lots 04235N MK 07 at Tuas (Tuas Plannin g Area) Jurong Shipyard $ 53,892,507.29
19 Proposed Internal Road & Drainage System for Proposed Docks,Wharves,Quay and other ancillary works in Shipyard (P1) MK07 on lots 04053P PT & 044129N PT at Tuas South, Tuas View Extension for M/s Jurong Shipyard Pte Ltd Jurong Shipyard $24,537,371.17
20 Construction of Road, Drains and Sewers at Tuas South View JTC $ 7,613,239.00
21 Construction of Retaining Wall System and Civil Works at Bukit Gombak Mindef $11,498,666.00
22 Soil Improvement and Proposed Roads,Drains and Sewers at Tuas South Avenue 7 & 9 JTC $ 6,666,566.00

 

Completed Projects in Last 10 Years

as Sub-Contractor

No. Project Title Owner Contract Amt
1 Improvement To Sungei Punggol Contract C8 PUB  $ 2,621,375.00
2 Slope Stabilization At Fort Canning Park Nparks  $ 844,645.00
3 ​Site Clearance and Close Turfing At Sembawang Town (Batch 1)  HDB  $ 1,764,000.00
4 Site Clearance and Turfing Works At Punggol Town (Batch 2) HDB  $ 352,231.20
5 Bulk Liquid Products Terminal at Jurong Island Horizon  $ 5,677,958.88
6 Improvement To Sungei Punggol Contract C9 PUB  $ 3,056,782.68
7 Telok Blangah Flyover LTA  $ 60,000.00
8 Banyan Integrated Terminal Phase (I) Jurong Island Vopak  $ 88,957.00
9 Proposed Tankstore Storage Expansion Project Phase 5, Pulau Busing Tankstore  $ 6,550,000.00
10 Petroleum Storage & Related Facilities ExxonMobil  $ 2,619,119.84
11 Bulk Liquid Products Terminal at Jurong Island (Additional 6 nos. Tank Foundation) Horizon  $ 1,800,000.00
12 Proposed  Bulk Liquid Products Terminal Phase at Jurong Island – Phase 3 Horizon  $ 4,138,528.20
13 Singapore Parallel Train Project, Jurong Island – Site Clearance Works New Polymer Storage ExxonMobil  $ 856,000.00
14 Construction of Tank Foundation (1 No) for proposed Blending at 168 Sakra Place, Jurong Island  Tate & Lyle  $ 251,461.80
15 Neste Oil OYJ at Tuas South Ave 9 Technip  $ 3,216,490.00
16 Bayfront Avenue Road Works – Roadworks & Drain (Area 2) MBS  $ 5,725,929.00
17 Neste Oil J183 – Earthworks and Lean Concrete Works Technip  $ 5,558,683.27
18 Proposed Construction of Road Works at Tuas South Avenue 2 Kolette  $ 655,874.22
19 Construction of Punggol Walk, Sumang Link and Vehicular Bridge at Punggol Walk across Punggol Waterway HDB $ 239,4451.10
20 Site Clearance Works,Construction of washing Bay & Temporary Site access Lanxess  $ 470,000.00
21 Proposed Boardwalk at Sentosa  $ 136,934.31
22 Construction of Roads, Drains, Sewers, Soil Improvement and Ancillary Works at Tuas View Extension Phase 3A JTC  $ 20,679,800.00
23 Site Preparation Works at proposed Jurong Aromatics Complex Project  SK Engineering & Construction  $ 856,227.60
24 Micro-piles Project in Singapore at Various Sites  $ 5,945,059.00
25 Earthworks (Excavate, Transport of Sand, Construct Sand Embankment for Surcharge and Remove after Surcharge)  Jurong Shipyard  $ 1,860,000.00